Hi,

Any help would be greatly appreciated.

I have introduced a task completed column and it has a drop down with two selections. Completed/Not completed. Thats all fine.

There are 13 tasks in total for each activity. I want to show the percentage completed...say 11 are saying completed, 2 are saying not completed.

I cant get a formula in the next column to show this (e.g 84 complete) and this would change as each line item is changed to either completed or not completed....

I bet you are all laughing at me but it been years and I am bit out of touch!

 

D.

 
Posted : 18/10/2021 9:23 pm
(@mynda)
Posts: 4761
Member Admin
 

Hi David,

Welcome to our forum! No silly questions here 🙂

You can use the COUNTIF function to count how many tasks are completed, which can then be divided by the total tasks calculated using COUNTA on the task column. I hope that points you in the right direction. If you're still stuck, please share your file so we can give you a solution based on your data.