Project Management Dashboard

5 Posts
2 Users
0 Reactions
57 Views
(@lawlortonyhotmail-com)
Posts: 3
Active Member
Topic starter
 

What is the best formula to use so I can calculate task completed against not completed given today’s date?

e.g. If a task is forecasted to take 10 days but after 7 days have elapsed task is only 3 days complete – I would like to use some conditional formatting highlighting a such based on a formula.

Task

10 days = 100%

7 Days Elapsed - Forecast should be 70% complete (Linear extrapolation example)

However

Task - 3 Days Complete - Actual will be 30% Complete

The difference is -40%

Thanks

Tony

 
Posted : 05/01/2021 12:31 pm
(@catalinb)
Posts: 1937
Member Admin
 

Hi Tony,

Can you upload a sample file with your data structure?

 
Posted : 06/01/2021 11:17 pm
(@lawlortonyhotmail-com)
Posts: 3
Active Member
Topic starter
 

Hi Catalin - many thanks for helping that's really kind.

I have uploaded the file attached.

Could you look at the data tab columns I, J, K?

 

Thanks

Tony

Any questions my email is [email protected] 

 
Posted : 07/01/2021 9:18 am
(@lawlortonyhotmail-com)
Posts: 3
Active Member
Topic starter
 

Attachment included

 
Posted : 07/01/2021 9:21 am
(@catalinb)
Posts: 1937
Member Admin
 

Hi Tony,

Please check the file attached, see if that solves your problem. Looks more like a math problem, not excel.

 
Posted : 08/01/2021 3:02 am