Hi

 

looking a bit of help around a Gantt and building in days to only include 2 weekdays as this is all that will be allocated per week for a project.

do i use the workday.intl or a different formula?, i looked at the workday.intl and it only allows the removal of two days in a week?

hope this makes sense

Jacqui

 
Posted : 13/04/2022 4:38 pm
(@mynda)
Posts: 4760
Member Admin
 

Hi Jacqui,

It depends on whether those workdays are sequential or not. e.g. are they Monday and Tuesday or Monday and Thursday? Also, please confirm that what you're asking for is an automated way to generate a list of dates?

Mynda

 
Posted : 13/04/2022 7:26 pm
(@jacqs)
Posts: 7
Active Member
Topic starter
 

Hi Mynda

the days are Thur, FRi as a part time worker - just looking for the gantt to reflect the days that are available to work on the project that will be the two days a week, and also hoping to add in holidays as well.

 

thanks 

jacqui

 
Posted : 14/04/2022 2:30 am
(@mynda)
Posts: 4760
Member Admin
 

Hi Jacqui,

This formula will give you a list of Thursday and Friday dates where A1 contains the first date you want to start at:

=WORKDAY.INTL(A1,1,"1110011")

Copy down or across as many cells as required

You can add the holidays to the last argument that I have omitted.

Mynda

 
Posted : 14/04/2022 7:08 am
(@jacqs)
Posts: 7
Active Member
Topic starter
 

Mynda

your a genius

thank you that's worked

Jacqui

 
Posted : 14/04/2022 12:12 pm